Walk to the Bethesda Avenue trailhead near Ourisman Plaza this week and you'll still find the same chain-link fence that's been there since September 2017: a detour sign pointing toward Jones Bridge Road, and a stretch of orange construction barrier where the gravel path used to continue toward Silver Spring. Nine years is long enough that an entire cohort of Bethesda-Chevy Chase High School students has grown up, learned to ride the on-road detour to school, and graduated without ever seeing the trail's Silver Spring half in its original form.
That's supposed to change this fall. The Coalition for the Capital Crescent Trail, the volunteer group that has tracked the trail's fate since the 1980s, still lists the reopening as tentative for fall 2026 on its own site. What almost nobody is saying out loud is that the version reopening this fall solves most of the trail's old problems and creates one new one, at the exact spot where the old trail was actually safer than what's coming back.
Before 2017, the Capital Crescent Trail ran as a single unbroken gravel path from Bethesda through a tunnel under Wisconsin Avenue, over Rock Creek on a trestle, and on to Silver Spring. It was, by any measure, one of the most heavily used rail trails in the country, carrying more than a million walkers, joggers, and cyclists a year before Purple Line construction closed the eastern half.
The closure pushed everyone onto Jones Bridge Road, a stretch with no marked bike lane and not much of a shoulder. County Council Member Andrew Friedson has pressed Purple Line officials for years on why the trail couldn't reopen faster while trains were still being tested on the light-rail line next to it, arguing that residents had already waited through enough delays. The frustration wasn't abstract. This is a commuter corridor for people who live in that part of the county, not just a scenic detour for weekend rides.
The reopening isn't one ribbon-cutting. It's the tail end of a phased construction schedule that's been running in pieces for years, and knowing the pieces changes how you should think about "the trail is back."
The first physically completed piece of the new alignment was a roughly 670-foot stretch across the new Talbot Avenue Bridge, which opened in May 2024. That gave trail advocates their first tangible proof the project was actually moving after years of delay. Closer to Bethesda, the Capital Crescent Surface Trail, a companion project built by Montgomery County's Department of Transportation, has been going up in phases along 47th Street in the Town of Chevy Chase. Phase 2 of that project, a 10-foot-wide shared-use path connecting Willow Avenue to the Elm Street Park promenade, broke ground in mid-October 2025, with pedestrian detours and flagging in place for the duration and work expected to run through the winter.
From Elm Street Park, the surface trail ties into the segment built alongside the Purple Line tracks themselves. The Coalition for the Capital Crescent Trail describes that segment as including a dedicated bridge over Connecticut Avenue and an underpass at Jones Mill Road, plus an elevated, off-street path carrying the trail into downtown Silver Spring at the Transit Center, keeping cyclists and walkers separated from both car traffic and the light rail at nearly every crossing.
Here's how the old trail and the version reopening this fall actually compare:
| Old interim trail (pre-2017) | Trail reopening this fall | |
|---|---|---|
| Surface | Unpaved, crushed stone | Fully paved, 12 feet wide with 2-foot buffers |
| Connecticut Avenue crossing | At-grade street crossing | New dedicated bridge |
| Jones Mill Road crossing | At-grade street crossing | New underpass |
| Wisconsin Avenue crossing | Tunnel underneath the street | At-grade street crossing |
| Silver Spring connection | None; trail ended at Lyttonsville | New elevated path into the Transit Center |
Look at that middle row again. Every crossing on the new alignment gets safer except the one at Wisconsin Avenue, which gets worse than what existed before the trail closed at all.
The original plan called for a dedicated tunnel to carry trail traffic under Wisconsin Avenue, the same six-lane crossing that trail users used to pass beneath instead of navigating on foot or by bike. Montgomery County actually approved funding for that tunnel once. In 2020, the County Council tentatively approved $54.9 million to build it, separate from but adjacent to the Purple Line's Bethesda station.
That money never made it into an actual construction budget. County Executive Marc Elrich omitted the tunnel from the county's capital budgets in 2020, 2022, and 2024. By 2024, when the Council considered adding it back in, the projected cost had climbed from $55 million to $82 million, and the votes weren't there to fund it. As of the most recent reporting on the county's stretched capital budget in January of this year, the tunnel remains unfunded and off the schedule entirely.
What that means in practice: when the trail reopens this fall with new bridges over Connecticut Avenue and a new underpass at Jones Mill Road, the one crossing that used to run underneath the street will instead run across it, at grade, with whatever traffic light and crosswalk configuration the county eventually settles on. Some trail advocates have speculated the tunnel could eventually get funded through a future redevelopment project near Elm Street, but nothing like that is on the county's books right now.
If you used to ride this stretch before 2017, expect the return route to look familiar in outline even though nearly everything underfoot is new. The trail still starts on Bethesda Avenue, still runs through the Town of Chevy Chase along the realigned surface path, and still ends up in Elm Street Park before joining the rebuilt alignment toward Silver Spring. Budget a few extra minutes at Wisconsin Avenue until the county settles on how that crossing gets signed and signaled, especially if you're riding with kids or commuting through there during rush hour.
If you're new to the neighborhood and have only known the trail as a closed gravel path with a detour sign, this fall is the first real chance to see what nine years of construction actually bought. The paved, grade-separated sections should genuinely improve the daily experience of getting around Bethesda and Chevy Chase without a car, and the new path into the Silver Spring Transit Center opens up a longer through-route than residents on this side have had for nearly a decade.
Either way, the headline "the trail is reopening" deserves an asterisk that most coverage has skipped past. What's coming back this fall is safer than what closed in 2017 at nearly every point except one, and that one point is the same six-lane street a lot of Bethesda residents cross on foot or by bike multiple times a week.
If you're thinking about what neighborhoods like Chevy Chase and Bethesda have to offer beyond the headline amenities, that kind of on-the-ground detail is exactly what shapes daily life here long after the for-sale sign comes down. If you'd like to talk through what's actually changing in this part of the DMV, whether you're weighing a move or just trying to understand the place you already call home, Jesse Oakley is happy to walk through it with you. Book a Consultation whenever you're ready.
OUR VALUE AND COMMITMENT TO YOU. You work hard to make a statement about yourself, your beliefs, and who you want to become – don't settle for anything less than the best in the business. We value individuality, beauty, transparency, and thought. The homes we are going to show you reflect that. We recommend lenders, contractors, and title companies and have a thorough knowledge of DC neighborhoods.